GITEC Consult
GmbH |
|
Integrated Consulting Services Worldwide is our Programme |
| |
| |
|
Rehabilitation of Open Drains in
the North Qena Directorate |
| |
|
Location North Qena, Upper
Egypt |
|
Client Egyptian Public
Authority for Drainage Projects (EPADP) |
|
Financing German Financial
Cooperation (KfW) |
|
Period 2002 – 2003 |
|
Value of Services 0.300
million US$ |
| |
| |
| Project Description |
| |
| A well functioning drainage
infrastructure is an indispensable precondition for increased
and stable agricultural production. The drainage system of the
Qena North General Directorate was found to be in a state of
advanced deterioration, only partially fulfilling its prime task
of keeping the groundwater table below crops’ root zone. Drains
are excessively widened by inappropriate maintenance activities
and subsequent slope slides endangering adjacent buildings,
roads, railway tracks and agricultural fields.
Rehabilitation in its conventional
sense, i.e. to reinstate a structure to its design shape and dimensions usually is a very costly affair. The major task of
this feasibility study therefore was to develop rehabilitation
methods that are reinstating the drains’ basic task and at the
same time are improving potential deficiencies inherent in the
original design, and which are being cost effective, sustainable
and universally applicable. |
| |
| |
| Scope of
Services |
| |
Scope of Services Feasibility
study:
- Analysis of cause of damage of 30 km of drains (10% of
total drains in Qena North General Directorate)
- Elaboration of
a methodology of assessment of damage and classification of
rehabilitation need
- Development of appropriate standard rehabilitation methods
- Economic justification of
rehabilitation
- Identification of emergency rehabilitation
needs, bills of quantities and cost estimates
- Preparation of a
rehabilitation programme for 307 km of drains
|
| |